Project Overview
Buildcorp needed to cut out a section of suspended concrete slab and remove part of a load-bearing masonry wall beneath a fire stair landing during renovation works in Surry Hills. Removing the wall would take away the load path for the landing and slab above, and the demolition zone had to stay clear of temporary works.
Legend Hire engineered a needle propping system combining custom structural steel needle beams, the Legend 50T Modular Propping System and tilt prop bracing. The needles picked up the structure above the opening and carried it to ground outside the work area, allowing demolition and construction of the new structure to proceed safely.
The Challenge
Buildcorp’s renovation scope required a portion of the existing suspended slab to be cut out and a section of load-bearing masonry removed beneath a fire stair landing. The wall carried the landing and slab loads to ground. Once it was removed, those elements had no support.


Three constraints shaped the solution:
- Lost load path. The masonry carried the landing’s dead load, stair imposed loads and the adjacent slab. All of that had to be transferred into temporary works before demolition began.
- Clear demolition zone. Conventional back propping places props directly beneath the supported element. Here, the area beneath was the demolition zone, so supports had to sit outside it.
- Slab cut edge. Cutting the slab creates a new free edge with exposed reinforcement and reduced continuity. The remaining slab had to stay supported through the cut.
Engineering Considerations
- Load transfer. Load path: slab and landing > masonry above the opening > steel needle beams > Legend 50T towers > bearing at lower level.
- Clear span. Needle beams spanned the demolition zone so the towers could bear outside it.
- Lateral stability. Tall modular towers carrying needle beams need restraint. Tilt props and tube bracing provided it.
- Controlled bearing. Screw jack heads brought each needle into firm bearing and pre-load before any masonry was removed.
- Sequencing. Propping was installed and verified before the slab was cut or the wall removed.
The Solution
Legend Hire proposed a custom structural steel needle propping detail combined with the Legend 50T Modular Propping System and tilt prop bracing.
Steel needle beams were installed through penetrations in the masonry above the removal zone, picking up the wall and landing above the new opening. Each needle end bore on a Legend 50T modular prop tower positioned outside the demolition footprint, founded on the lower slab floor. Towers were braced with scaffold tube and couplers, and screw jack heads were adjusted to bring the needles into firm bearing.
Steel tilt props were raked from head plates fixed to the slab soffit down to brackets at the needle and wall supports, providing lateral restraint to the system and supplementary support to the slab adjacent to the cut edge.
The modular 50T system allowed every component to be hand-carried into a confined stairwell and built up in position. Installation was coordinated with Buildcorp’s demolition sequence: propping installed, verified, then slab cutting and masonry removal.



Equipment Used
- Custom fabricated structural steel needle beams
- Legend 50T Modular Propping System with adjustable screw jack heads
- Steel tilt props with soffit head plates and wall brackets
- Scaffold tube and coupler bracing
The Outcome
The fire stair landing, load-bearing wall and suspended slab remained supported throughout the slab cutting and demolition works. Buildcorp completed the removal and constructed the new structure beneath the needles with no measurable movement or unplanned stoppage.
Related Projects
Legend Hire has delivered related temporary works for Buildcorp in Surry Hills, including back propping a concrete stair landing], column needling with 100T hydraulic jacks for a lift shaft, and a waler and raking prop system for retaining wall underpinning. Similar methods were used for cantilever needle propping in Stanmore and needle beam wall support in Ultimo.
Frequently Asked Questions
Needle propping is a temporary works method where steel beams, called needles, are passed through a wall to pick up its load above an opening. The needles bear on props either side, carrying the structure to ground while the wall below is removed or altered.
Needle propping is used when the area directly beneath the supported element must stay clear, such as a demolition zone, a new opening or an excavation. The needles span the work zone so the props can bear outside it.
The wall and slab loads are first transferred into an engineered temporary propping system, such as needle beams on modular props. The system is brought into firm bearing and checked before any masonry is removed, so the slab is supported throughout demolition.
Tilt props are raking steel props that provide lateral restraint and diagonal support to walls, slabs and propping systems. They prevent sway and movement while the main vertical loads are carried by the primary propping.
Planning a Wall or Slab Removal?
Legend Hire engineers and supplies needle propping, modular propping and tilt prop systems for structural alterations, demolition and refurbishment works. Our temporary works engineering team designs each system around your structure, site constraints and demolition sequence. Call 1300 890 890 or Email legends@legendhire.com.au