This project became both a test of OMAC Italy’s equipment in local conditions and an example of how the right preparation and support can keep high-stakes projects on track.
The Challenge
- Tight deadline: Equipment needed on site and operational by Friday afternoon to meet mobilisation plans.
- New technology: The client had never used OMAC Italy machines before and had long relied on other brands.
- Freight delays: Three 40ft containers were still in transit, creating a real risk of missing the deadline.
With the stringing of single and twin conductors being a critical path task, any delay could cause significant setbacks for the overall project schedule.



The Response
Legend Hire took a hands-on approach to keep the project moving:
- Maintained clear communication with the client throughout the shipping process.
- Coordinated with freight partners to secure a rare early-morning port release and immediate transport to our Penrith branch.
- Had a prepared crew ready with tools, fluids, fuels, and OEM support in place before the containers arrived.
Within six hours of delivery, the OMAC Italy machines were:
- Unpacked
- Fully serviced
- Inspected and tested
- Ready for collection at 1:00 PM that same day

First Impressions & Operator Training
Legend Hire technicians stayed on site over the weekend to assist with setup of the puller/tensioners, reel trolleys, and drum elevators. On Sunday, an OMAC Italy specialist provided hands-on training for the operators.
By Monday, initial hesitation had shifted to positive feedback:
“These machines are fantastic to operate. We can’t believe there wasn’t another option like this before.”
Operators noted:
- Easier controls and faster learning compared to competing brands
- Features and functions not previously available in their fleet
- Smooth, precise performance in challenging conditions
The Pull: Tight Space, Twin Conductors, 90-Degree Bend
The real test came during live operation:
- Tight pole spacing
- A sharp 90° bend in the alignment
- Triple sheave block and balancing headboard requirements
Despite concerns about clearance, the OMAC Italy 10T Puller/Tensioners delivered:
- Consistent pulling power
- Fine control for delicate manoeuvres
- Adaptability to changing site needs
The outcome was an on-time, incident-free completion of a complex and high-risk pull.
Results & Impact
- First operational use of OMAC Italy puller/tensioners in Australia
- No downtime despite freight challenges
- Full operator competence before live operation
- Strong customer confidence leading to potential future projects
Why It Matters
This was more than a standard equipment hire—it demonstrated:
- The capability of OMAC Italy technology in Australian transmission line projects
- The value of detailed preparation and technical support in meeting deadlines
- A contribution to renewable energy infrastructure in Australia