Steel Column Propping for Loading Dock Excavation

Pemulwuy, NSW

GC Built needed an existing steel column braced while its footing was partially excavated for a new loading dock in Pemulwuy, NSW. Legend Hire engineered a Legend 50T Modular Propping System that bridges over an internal building to restrain the column.

Project: Steel column propping for loading dock excavation
Location: Pemulwuy, NSW
Sector: Industrial / Warehouse
Client: GC Built
Services Provided: Temporary works engineering, propping supply
Equipment Used: Legend 50T Modular Propping System, raking brace members, column connection brackets, scaffold tube restraints

Project Overview

GC Built engaged Legend Hire to temporarily brace an existing steel column inside a Pemulwuy, NSW warehouse while external excavation was carried out for a new loading dock. The excavation required partial removal of the column’s concrete footing, which reduced the support and restraint at the column base. With an existing internal building positioned directly in front of the column, the propping could not bear on or disturb that structure. Legend Hire’s Engineering team designed a temporary bracing system using the Legend 50T Modular Propping System. The system bridges over the internal building and restrains the column, so excavation could proceed safely.

The Challenge

The new loading dock required excavation along the external face of the warehouse, cutting into the concrete footing beneath an existing steel portal column. Once the footing was partially removed, the column’s base support and lateral restraint would be reduced while it continued to carry roof and wall loads.

Conventional raking props could not be used. An occupied internal building stood directly in front of the column and could not be removed, loaded or damaged. The temporary works therefore had to reach the column from the slab without bearing on the internal structure, within the clearance between that building’s roof and the warehouse framing.

The solutions

Legend Hire’s Engineering team designed a bridging frame from the Legend 50T Modular Propping System. Vertical modular legs were founded on the warehouse slab either side of the internal building. They were connected by horizontal 50T members spanning over its roof to form a portal frame clear of the existing structure.

Raking brace members were connected from this frame to the steel column, creating a triangulated load path that restrains the column and transfers bracing forces back to the slab. Scaffold tube ties were installed between the frame legs for additional stability. The system was installed before excavation began, and coordinated with GC Built’s excavation sequence.

Equipment Used

  • Legend 50T Modular Propping System (vertical legs and horizontal spanning members)
  • Modular raking brace members with adjustable ends
  • Column connection brackets
  • Base plates
  • Scaffold tube and fittings for lateral ties

The Outcome

The Legend 50T bracing system held the steel column stable throughout the footing excavation, allowing GC Built to construct the new loading dock without disturbing the existing internal building. The works were completed with zero incidents and the excavation programme was maintained. The project shows how modular propping can be configured to bridge over existing structures where conventional raking props have no landing point.

Frequently Asked Questions

How is a steel column supported when its footing is excavated?

The column is restrained with temporary bracing or propping that provides an alternative load path to ground before any footing is removed. The bracing stays in place until the permanent footing is reinstated.

Can propping be installed over an existing structure?

Yes. A modular propping system can be configured as a bridging frame that spans over an existing building and bears only on the slab either side.

What is the Legend 50T Modular Propping System?

It is a heavy-duty modular steel propping system that can be assembled as vertical props, horizontal spanning members or raking braces, so one system can carry vertical and lateral loads.

When are temporary works needed for loading dock construction?

They are needed whenever excavation for a dock wall or ramp undermines existing footings, columns or slabs, or when it runs close to them.