Project: Large-diameter pipeline installation, open trench
Sector: Civil infrastructure, water and utilities
Services provided: Trench shoring hire, trench access and rescue equipment, road safety barrier hire
Equipment used: Legend Pro aluminium shoring boxes (7.2m, 5m, 3m), VertiShore LR hydraulic shoring, shoring box handrails, ladder access platforms, Xtirpa davit arm, 24m fall-arrest retrieval winch, Lo Ro TL2 water-filled barriers, anti-gawk screens
Project Overview
Legend Hire supplied an integrated trench shoring and road safety system for the installation of a large-diameter pipeline along a residential street. The trench ran between a live road and residential property boundaries, leaving a narrow working corridor, and the alignment crossed existing underground services.
Legend Pro aluminum shoring boxes provided continuous trench support along the main run, with 1505mm internal clearance to allow the pipe to pass beneath the spreaders. VertiShore hydraulic shoring supported sections where a shoring box could not be placed. Handrails, ladder access platforms and a davit arm with fall-arrest retrieval winch managed edge protection, access and rescue, while TL2 water-filled barriers with anti-gawk screens separated the work zone from passing traffic


The Challenge
The contractor needed to excavate and lay a large-diameter pipeline along a residential street while keeping a section of the road open to traffic. The site presented several constraints:
- Trench stability: The excavation depth required the trench walls to be supported against collapse for the full length of the open trench.
- Restricted corridor: Property fences sat directly alongside one side of the trench and a live traffic lane on the other, leaving limited room for excavator operation, spoil and pipe handling.
- Pipe clearance: The pipe diameter required shoring with enough clear height beneath the spreaders to lower and position pipe sections without disturbing the shoring.
- Public interface: Passing vehicles and pedestrians had to be separated from the excavation, and driver distraction near an open trench needed to be controlled.
- Access and rescue: Workers required safe access into the trench, edge protection at the trench line and a retrieval method in an emergency.
The solution
Legend Hire configured a combined shoring, access and traffic-separation system matched to the trench geometry and site constraints.
Aluminium shoring boxes for the main run. Legend Pro aluminium shoring boxes in 7.2m, 5m and 3m lengths were installed along the trench alignment. Using three box lengths allowed the shored length to be matched to each section of the alignment and adjusted around obstructions. Each box provided 1505mm of internal clearance beneath the spreaders, allowing pipe sections to be lowered and laid inside the protected zone.
The lighter weight of aluminium boxes made them easier to install and reposition using the excavator already operating on site within the tight corridor.
VertiShore hydraulic shoring at constrained sections. VertiShore LR V1500 hydraulic shores (1500mm rails, adjustable from 1320mm to 2235mm) provided trench support where a shoring box could not be placed, such as around crossing services. VertiShores are lowered, pressurised with a high-volume hand pump and removed with removal hooks from the surface, so the trench is supported before anyone enters it and no worker is exposed to an unsupported face during installation or extraction.
Edge protection, access and rescue. 3000mm handrails mounted to the shoring box panels formed continuous edge protection along the trench line. Ladder access platforms provided a controlled point of entry and exit. An Xtirpa shoring-type davit arm with a 24m fall-arrest and retrieval winch gave the crew a rescue and retrieval capability for workers inside the trench.
Traffic separation. Red Lo Ro TL2 water-filled cable barriers created a continuous separation line between the live road and the work zone, with anti-gawk screens fitted to reduce driver distraction and screen the excavation from passing traffic.

Project Considerations
- Shoring selection: Shoring boxes suited the continuous, linear alignment of this pipeline trench. Deeper or larger excavations call for other systems, such as the slide rail shoring system used for an underground water tank installation, or the deep trench shoring used for a 6m sewer installation.
- Rescue planning: Retrieval equipment was supplied with the shoring rather than as an afterthought, so emergency retrieval was available from the first day of excavation.
- Surcharge from road and plant: The live road and excavator operated close to the trench edge. Barrier placement and plant positioning were set to manage loads adjacent to the excavation
The Outcome
The combined system allowed the pipeline to be laid inside a fully supported trench while the adjacent road remained open to traffic.
- Trench walls supported for the length of the open excavation, including at constrained sections
- Pipe sections lowered and laid within the protected zone using the boxes’ 1505mm internal clearance
- Continuous edge protection, controlled access and emergency retrieval in place throughout excavation
- Work zone physically separated from live traffic, with driver distraction reduced by anti-gawk screening
Frequently Asked Questions
A trench shoring box is a pre-assembled shield of two side panels held apart by adjustable spreaders. It is lowered into an excavation to support the trench walls and protect workers inside. Aluminium shoring boxes are lighter than steel, which makes them suited to smaller excavators and tight urban sites.
Under the model WHS Regulations, a trench 1.5m or deeper must be protected against collapse, typically by shoring, benching or battering. Shoring is usually the practical option where space is limited, such as alongside roads, fences and existing structures.
A VertiShore is a lightweight hydraulic shore made of two vertical rails connected by hydraulic rams. It is installed and removed from the surface and suits short sections, service crossings and locations where a shoring box cannot be placed.
Water-filled barriers such as the TL2-rated Lo Ro system create a physical separation between traffic and the work zone. Anti-gawk screens fitted to the barriers reduce driver distraction and screen the excavation from view.